How to delay the dates for the test cycle and project
Problem
I added an end date to my project however I have met the end date. Now I can not use the EAS to assign test cases for next week. What should I do?
Cause
How to delay the dates for the test cycle phase
Fix
The Project End Date is the only hard date contained in Zephyr. If your project’s end date was tomorrow, for example, you are not able to use the EAS module to assign test cases next week.
In order to delay the date of your Project, please login as a test manager and scroll to the Project setup Application. Now delay the end date of the Project related to that cycle according to your requirement. Finally, go to the phase which you want to be delayed and delay the phase duration.
Knowledge Document Information
-—————————————————————————————————————–-—————————————————––
Title: How to delay the dates for the test cycle phase
Product: Enterprise Edition, Community Edition
Version: 4.6
Summary: I added an end date to my project however I have met the end date. Now I can not use the EAS to assign test cases for next week. What should I do?
-———————————————————————————————————————————————————————––